Two London based construction companies were prosecuted after a Health and Safety Executive (HSE) inspection identified serious safety breaches on a double basement construction project. Both companies had been made aware of the dangers on the site previously by an independent consultant, but they failed to act on the recommendations.
The HSE inspection found workers were at risk from falling into deep excavations and there were no propping arrangements to ensure the stability of excavations or the existing building. The inspector immediately shut down the site.
The investigation by HSE found that an independent consultant had raised the same concerns a few months previous but the recommendations had been ignored.
The Principal Contractor Lifehouse (London) Ltd appointed Nu Space Design Ltd as the contractor to carry out the excavation work and one its directors as the site manager. Neither company appointed a competent person to inspect the excavations to ensure they were safe.
Lifehouse (London) Ltd of 28 Church Road, Stanmore, HA7 4XR pleaded guilty to breaching Regulation 13(1) of the Construction (Design and Management) Regulations 2015 (CDM) and was fined £24,000 and ordered to pay £1,141.50 in costs.
Nu Space (Design) Ltd of 39 Wimborne Avenue, Hayes, UB4 0HQ pleaded guilty to breaching CDM Regulation 15(2) and was fined £20,000 and ordered to pay £1,067.10 in costs.
HSE inspector Andrew Verrall-Withers commented after the hearing: “When carrying out any construction work, whether new build or refurbishments you have to ensure it is done safely. In this case they should have appointed a competent person to carry out regular inspections of the excavations to ensure they did not collapse onto workers or cause the building to become unstable during the work”.
Leave A Comment
You must be logged in to post a comment.